In India, supply chain management often relies on a series of contracts and subcontracts, which hold a business’s operational stability together. However, when a Breach of Contract in the Supply Chain arises—whether due to non-delivery, late delivery, quality defects or other disruptions—the impact can ripple across industries. 

Companies face challenges not only in holding parties accountable but also in mitigating financial and operational losses. Legal remedies and specific legal frameworks under the Indian Contract Act, 1872, become pivotal in such scenarios, along with landmark court decisions that shape the obligations and remedies available to impacted businesses.

 

Legal Provisions and Common Causes of Breach of Contract in the Supply Chain

Under the Indian Contract Act, 1872, several clauses address the nuances of a Breach of Contract in the Supply Chain. Sections 73 and 74, for example, enable aggrieved parties to seek compensation for direct losses. 

Some typical causes of breach in supply chains include delivery delays, non-compliance with quality standards, failure to meet agreed quantities, and disruptions caused by external factors like economic crises or natural disasters.

A notable legal provision that parties often invoke is the “Force Majeure” clause, which temporarily relieves parties from liability due to unforeseen, unavoidable events. During the COVID-19 pandemic, for example, several supply contracts invoked force majeure. However, the Indian judiciary has ruled that force majeure only applies if specified in the contract, reinforcing that general disruptions may not automatically justify a breach​.

Some sections of the Indian Contract Act, 1872 are relevant in understanding the legal framework surrounding Breach of Contract in the Supply Chain. These sections detail the consequences, obligations and available remedies when a breach occurs:

  • Section 73: This section defines the fundamental principles of damages in Indian contract law. It states that the party responsible for a breach must compensate the affected party for any loss or damage resulting directly from the breach. The losses should be reasonably foreseeable and naturally arising from the breach. 

This provision is particularly applicable to supply chain disruptions where failure to deliver or delays can lead to quantifiable business losses​.

Claiming Damages

As per Section 73 of the Indian Contract Act, the primary remedy for breach is compensation in the form of damages. Affected parties may seek either general damages for losses that are the natural outcome of the breach or special damages if the breach leads to additional losses due to specific circumstances (e.g., costs to procure alternate supplies).

  • Section 74: This section addresses contracts with predetermined penalties or liquidated damages. 

For example, in supply chain contracts, parties often stipulate penalties if a supplier fails to deliver goods on time. Section 74 allows courts to award such damages, but only to a “reasonable” extent rather than the stipulated amount if it’s deemed excessive​.

Liquidated Damages

Liquidated Damages (Section 74) are common in supply chain contracts. These are pre-agreed upon penalties specified in the contract for non-performance, such as delays in delivery or failure to meet quality standards. Courts have the discretion to reduce excessive liquidated damages, ensuring fairness in cases where stipulated penalties are disproportionate to the actual loss.

  • Section 75: This provision entitles a party to compensation if they have rightfully rescinded a contract due to a breach. In the context of a supply chain, if a business rightfully terminates a contract due to the supplier’s default, they can claim compensation for any resultant losses, such as increased costs incurred when finding an alternative supplier​.

Rescission of Contract

When a breach significantly affects the contract’s purpose, the affected party may seek rescission, terminating the contract and freeing them from obligations. In addition, Section 75 of the Indian Contract Act grants the aggrieved party the right to compensation for losses incurred up to the point of rescission, including costs involved in securing alternative suppliers.

  • Specific Performance

For certain unique goods or services, parties may request the court to compel the breaching party to fulfill their contractual obligations rather than pay damages. However, courts typically reserve specific performance for cases involving non-substitutable goods (e.g., rare materials or goods manufactured to precise specifications)

 

Notable Case Studies in Breach of Contract in the Supply Chain

1. Hanuman Cotton Mills v. Tata Aircraft Ltd. (1969):

This case is a landmark in assessing “foreseeability” in the Indian context. Here, Tata Aircraft Ltd. faced difficulties due to delayed supplies, impacting their business operations. The court held that damages should be awarded only for foreseeable losses that naturally arise from the breach.

2. ONGC v. Saw Pipes Ltd. (2003):

This Supreme Court case focused on liquidated damages, upholding a party’s right to pre-agreed penalties in contracts. ONGC was awarded liquidated damages for delays, validating that supply chain agreements may include enforceable penalty clauses to prevent breaches. 

The court emphasized that stipulated damages in contracts must align with the actual losses incurred, highlighting the judiciary’s balanced approach towards penalty clauses​

3. BSNL v. Reliance Communication Ltd. (2011):

This case analyzed performance guarantees and liquidated damages. BSNL terminated a contract due to poor service, invoking a penalty clause. The court upheld BSNL’s right to penalties under the liquidated damages clause, demonstrating that performance guarantees in supply chain agreements can offer recourse when a breach occurs. 

 

Conclusion

In India, Breach of Contract in the Supply Chain carries significant legal, financial and reputational implications for businesses. Courts have consistently upheld the principles of foreseeability and reasonable compensation, ensuring that damages awarded align closely with actual losses incurred, thus preventing misuse of liquidated damages provisions.

Detailed and forward-looking contract clauses—including robust force majeure terms and enforceable penalty clauses—are essential to safeguard supply chain stability.

 

Why Choose MAHESHWARI & CO. for Supply Chain Contract Breaches

MAHESHWARI & CO. is recognized for its deep expertise in handling complex Breach of Contract in the Supply Chain cases. With a dedicated team specializing in commercial contract law, we provide effective legal solutions tailored to address supply chain disruptions, enforce contractual obligations, and recover losses. From enforcing liquidated damages to pursuing specific performance, our legal strategies are designed to protect your business interests while maintaining the stability of your supply chain.

 

FAQs on breach of contract in the supply chain

1. What constitutes a breach of contract in the supply chain, and how can it affect businesses?

A breach in the supply chain happens when a party, typically a supplier, fails to fulfill their contractual obligations—such as by missing delivery deadlines, supplying defective products, or failing to meet quality standards. 

This can lead to significant consequences for the buyer, including production delays, increased costs, or even a temporary halt in operations. In India, such breaches are governed by the Indian Contract Act, 1872, which lays out remedies like compensation and specific performance.

2. What legal remedies are available for breach of contract in the supply chain?

Remedies vary depending on the nature and terms of the contract, but they commonly include:

Damages: Compensatory damages for direct and foreseeable losses under Section 73 of the Indian Contract Act. If the contract includes a liquidated damages clause, the non-breaching party may claim a predetermined penalty amount.

Specific Performance: The court may order the breaching party to fulfill their contractual obligations, particularly if the breached contract involves unique goods or non-substitutable services.

Rescission: In cases of significant breach, the non-breaching party can seek to rescind or cancel the contract under Section 75, often with compensation for incurred costs​.

3. Can liquidated damages clauses effectively address delayed deliveries in supply chain agreements?

Yes, Indian contract law supports liquidated damages clauses as long as the penalty amount is deemed reasonable. Liquidated damages are a pre-agreed sum that the breaching party pays for delays or other forms of non-performance. Courts typically enforce such clauses under Section 74 but may adjust the amount if it appears disproportionate to the actual losses incurred.

4. How do force majeure clauses function in supply chain contracts, and what are their limitations?

Force majeure clauses exempt parties from liability in case of unforeseeable events like natural disasters, pandemics, or political upheaval that prevent contractual performance. Such clauses gained prominence during COVID-19, allowing parties to avoid breach claims when operations halted unexpectedly. 

However, these clauses have limitations—they only apply if the event truly prevents performance, not if it merely makes it inconvenient or costly. Courts require force majeure events to be clearly defined and documented in the contract to assess their legitimacy in a dispute​.

 

Explore More: Breach of Contract under Indian Law